Accelerator Test Facility (ATF) [1] is now under
construction in the TRISTAN Assembly Hall in order to generate
a extremely low emittance beam for linear collider studies. It
consists of 1.54 GeV S-band Linac, beam transport line, damping
ring and extraction line. The S-band Linac is an injector of the
damping ring which supplies a multi-bunch train beam which is
20 bunches with 2 ¥
1010 electrons/bunch and 2.8 ns bunch spacing. The
newly developed techniques which are high gradient accelerating
unit, precise alignment system, beam energy compensation system,
compact modulators, multi-bunch beam monitors are used in this
linac. The commissioning of the linac was held on November 1995.
The beam experiments on a high gradient acceleration and a beam
energy compensation for the transient beam loading were performed.
The results of these experiments are shown.
The main purpose of ATF is to develop an extremely
low emittance beam and to demonstrate that one of main key issue
of a linear collider is solvable. ATF linac is not only a injector
linac of the damping ring but also a test-stand of common key
components to realize a linear collider such as multi-bunch beam
generation, high gradient acceleration, beam loading compensation
and instrumentation development. The construction was started
since 1991 in the TRISTAN Assembly Hall in KEK which was a building
of 120 m ¥
50 m width. The reinforcement of the floor driving many piles
into the ground was done at first to support heavy concrete shield
blocks of tunnels and to avoid floor vibration. The construction
of linac was started on October 1992. The 80 MeV electron
beam by the preinjector part of the linac [2] has been utilized
to test structures and monitors since August 1993. The main part
of the linac and the beam transport line to the damping ring has
been constructed for about two years. The commissioning of the
linac was then held on November 1995. The accelerated beam energy
was 1.3 GeV for both single bunch and multibunch. In this stage,
the damping ring and the extraction line are still under construction.
The performance and development status of ATF linac are summarized
in detail. The beam experiments of high gradient acceleration
and beam loading compensation are also described.
The ATF linac summarized in Table 1 is consist of
80 MeV preinjector, 8 regular accelerating units, two unit
of energy compensating structures. The special concern on the
high gradient acceleration, beam loading compensation, active
alignment system and fast and precise beam instrumentation are
also paid.
Beam Energy for DR
Total Length Accelerator Structure Total length Total number Accelerating Field Maximum Peak Field Nominal with Beam RF Frequency Feed Peak Power Klystron Klystron Peak Power Klystron Pulse Length Number of Klystrons Pulse Compression Power Gain S-band Preinjector Beam Energy Number of Bunches Bunch Population Bunch Separation | 1.54 GeV
85 m (from Gun to linac end) 2 p/3 mode constant gradient 3 m
16 52 MV/m 30 MV/m 2.856 Ghz
200 MW/structure 80 MW/structure 4.5 ms 8 Two-iris SLED
5.0 (average) 80 MeV 20 2 ¥ 1010 electrons 2.8 ns |
80 MeV Preinjector of Linac [2]
The role of preinjector is to generate 20 multi-bunch of 2 ¥ 1010 electrons/bunch with 2.8 ns bunch spacing and to inject it to 1.54GeV Linac. Since the bunch length less than 10ps(FWHM) is required to meet the energy acceptance of the damping ring, the buncher cavities are designed to have low R/Q values in order to reduce beam induced voltage which affects to bunching of successive bunches.
The extraction of multi-bunch from ordinary thermionic
gun is done by applying RF wave of 357 MHz to the grid [3]. The
extracted bunch has 1ns (FWHM) and 3A peak current with 200 kV
energy. The bunch is shrunk to 15 ps (FWHM) by the two 357 MHz
SHB cavities and the 7 cell traveling-wave 2856 MHz buncher cavity.
After bunching, the bunches are accelerated up to 80MeV by a 3
m structure, then go into the Linac regular section. One klystron
is used in the preinjector which is operated at 60 MW, 1 µs
with no SLED. It supplies an rf power into the 3m structure together
with the buncher cavity.
High gradient accelerating unit [4]
An 1.54 GeV beam energy is required within about
85 m of total Linac length including preinjector, quadrupole magnets
and beam monitors, because of the limited length of the building.
A high gradient of 30 MeV/m is necessary for the beam acceleration.
The limit of accelerating gradient in the accelerating structure
is determined by the break down of the electrical field and the
intensity of the field emission current. Since the break down
comes from the field emission current, to reduce the field emission
current is a key point to get a high gradient field. From the
conclusion of the high gradient experiment which we have done
for several years, the effort for high gradient structure has
done as listed below;
1. keep cleanness during fabrication and tuning in order to avoid dust and contamination on the surface of the structure.
2. the input and output coupler are carefully designed to avoid field enhancement like tuning dimple.
3. use HIP (Hot Isostatic Press) OFHC for the disks to reduce voids between crystal grains.
As a result, a maximum peak gradient of 52 MV/m was achieved with 200 MW peak rf power input in the one of regular unit.
Using these high gradient structures, the regular
accelerating unit is composed by 80MW klystron, two-iris SLED
and two 3 m structures. This system can generate 400 MW peak
power rf from the SLED (200 MW peak power rf into 3 m structure)
and 240 MeV energy gain (Fig. 1).
Energy Compensation System
In multi-bunch acceleration, a beam energy decreases
from the front to the end gradually by a transient beam loading
of the structures. Since the maximum energy acceptance of damping
ring is ±1% and since a variation of bunch spacing is not
acceptable, the new energy compensation scheme for the multi-bunch
was developed. Using the accelerating structure which is operated
in slightly higher frequency, the front bunches can get deceleration
and the rear bunches can get acceleration. To cancel out an energy
spread within a bunch, the other structure which is operated in
lower frequency of the same amount with opposite slope is used.
With this system the energy spread among bunches can be reduced
from about 5% to 0.2% peak to peak. In order to simplify the timing
system, the frequency deviation was chosen to 4.327 MHz which
is just twice of damping ring revolution frequency [6]. Consequently
all of the frequencies are fully synchronized. The system consist
of two klystrons and 3 m structures which are operated in 2856+4.32
MHz and 2856-4.32 MHz each. The maximum output of klystron is
50 MW, 1 µs square wave which can compensate maximum 80 MeV
beam energy in one unit.
200 MW compact modulators [7]
A 200 MW modulator development has been continued
since 1987. In total eleven modulators, seven of them are supplied
by the one common DC power supply. Four of them are independent
type which are supplied by 200 V AC. The main effort of this development
is focused on the total size, stability and efficiencies which
will directly affect on the scale of the linear collider machine.
The use of the compact self-healing type capacitors makes the
PFN more compact. The packing of each device into the modulator
box was re-checked to make high density packing. By discarding
the electric standard for spacing of high voltage device in Japanese
industry, 1.5 m ¥
2.5 m width and 2.2 m height modulator was realized for the three
of them. To make a hold-on time of thyratron shorter, the charging
into the PFN is initiated by the command from the controller (command
charging). To avoid reverse voltage on the thyratron, a tail clipping
diode circuit are added. By these method, the lifetime of the
thyratron will be longer. The energy loss of the de-Qing circuit
is collected by a simple circuit which makes 5% saving of wall
plug power.
Wire Alignment System [4]
The stages of the linac have an active mover mechanism and wire position sensors. In order to monitor the stage position and to align the whole stages, two stretched wires are used with the length of about 85 m. The wires are stretched in both side from the preinjector stage to the end of the linac. The sag of wires are calculated in each sensor position as far as no kink on wires and assumption of uniform wires with no creep and no friction on the wheel. The center position of wire sensors mounted on the support stage are calibrated in its calculated position in the calibration stand. Each sensor mount is fixed to the reference surface of the stage which is machined with less than 10 µm in accuracy. In this way, when the stages are aligned so as to get the wire position into the center of the sensors, the reference surface of the stages are aligned to the wires in straight. The resolution of position sensor is 2.5 µm and the accuracy of center finding is ±30 µm. The wire position is detected by a synchronous detection of the signal from the differential coils using 60 kHz current on the wire.
Since the stretched wires had a big sag of a few
cm greater than the calculated value at the initial alignment,
the alignment of the stage has been done by using the telescope
and the alignment target. The alignment sections are divided to
five sections and connected them by partial superposition. As
the first result of the telescope alignment, the stage reference
edges were lied in the range of ±250 µm. The further
study will be done on this alignment problem.
Beam Position Monitors
In order to measure the orbit in the linac and the
beam transport line, the BPM system was installed and commissioned
on February 1996. The pickup chambers are 6 button-type BPM for
the pre-injector part and 24 stripline-type BPM for the linac
and the beam transport line. The stripline type BPM which has
80 mm length of strip and 30 mm inner diameter has a resolution
of 1 µm for 2 ¥
1010 beam charge together
with the high precision track&hold electronics [9]. Figure
2 shows the cross-section of the stripline BPM chamber used in
the linac. These BPM chamber are installed in the reference stage
girder of the linac by the precision support.
The relay multiplexing is used for the detection
electronics which consist of 5 set of the track&hold electronics
of x and y position detection. The measurement of beam position
is done by 6 pickups multiplexing for each set. The measured orbit
of the beam is corrected by the program "SAD". The convergence
of the correction into ±1 mm deviation is attained by around
4 iterations.
Multi-bunch Beam Monitors
In addition to ordinary monitors such as toroid current
monitor, screen profile monitor, stripline beam position monitor
and bunch length by streak-camera, we are developing bunch by
bunch position, size and current monitors which measures each
bunch in the 20 bunch train. The preliminary result of gated beam
size measurement done by using a fast gated camera on OTR light
and gated gamma detection in the wire scanner is reported in elsewhere
[1, 7]. The fast current measurement using wall-current monitor
and gated position measurement using fast sample-hold circuit
are now under developing.
Control System
The control computers are VAX cluster which consists
of one main control computer (alpha), one hardware interface computer
(VAX4000) which is connected to the hardware device by the CAMAC
serial highway, and four workstation terminals. V-system is adopted
as a control software for the window system. In order to connect
to the program 'SAD' running on the HP workstations in the different
place, and to support the experiment data processing, the Macintosh
computer is used together with the VAX station. As a real-time
control information, the CATV (cable TV broadcasting) system is
introduced for monitoring beam signals on the oscilloscope, screen
profile, streak-camera image and so on.
A high power test of the regular accelerating unit
has been done using one of the accelerating unit from January
8 to February 13, 1994. The power was raised up to 80 MW, 4.5 µs
at the output of the klystron. The input peak power of each 3m
structure was about 200 MW with SLED cavity. The total processing
time was about 600 hours with 200 hours system check and SLED
tuning. The rest units were processed from September 29 to November
28 1995 during night only. The day time was spent for the wiring
of magnet and monitors, alignment of the linac and construction
of the beam transport line. The power level of the klystron output
was reached to 44 MW average at the commissioning time. After
few months operation, it was raised to 62 MW average. The main
reason of this lower operation power level comes from the modulator
over-current trip initiated by the electrical noise.
The beam commissioning of ATF Linac was begun on
November 22 with insufficient rf processing level. The emittance
of 80 MeV injection beam was measured at first. Then the optics
which was the matching calculation result from 'SAD' by using
the measured emittance was set. The delay timings of rf pulse
with beam were adjusted by measuring a difference between BPM
signal and rf signal. The phase of rf then searched to get good
transmission. The orbit was also adjusted by using screen profile
monitors. Once the beam went through the linac, the rf phase and
timing were adjusted precisely to get the highest beam energy.
After few days above beam tuning, the single bunch of 1 ¥
1010 was accelerated up to 1.3 GeV by the average gradient
of 25.5 MeV/m, and the multibunch of 6 bunches/pulse were
also accelerated with the intensity 1 ¥
109/bunch. The energy spread of the single bunch was
1% FWHM and the normalized rms. emittance was 2 ¥
10-4. The intensity was
raised up to about 2 ¥
1010 during the operation for the several experiments.
However, the transmission ratio of the beam current from the exit
of preinjector to the end of the linac was about 60% at around
1 ¥
1010 or over. The reason of this low transmission was
investigated, and found that it came from the low energy tail
of the energy spread which slipped out from the acceptance of
the optics. The energy of the beam which is still below the required.
The reason comes from the modulator over-current trip problem
which is caused by an interference with an electrical noise. This
is now under fixing. On February 1996, the BPM system was installed
and commissioned as mentioned above. The measured orbit of the
beam is corrected by "SAD". The beam operation of linac
became easy than before. The linac is now operating routinely
for various beam experiments of linear collider R&D. To summarize
the performance of this linac, the achievement are listed in Table
2.
Maximum Beam Energy | 1.42 GeV |
Maximum Gradient with beam | 28.7 MV/m (average) |
Maximum Klystron Power | 62 MW (average) |
Accelerated Intensity: single bunch | 1.7 ¥ 1010 |
:20 multi-bunch | 7.65 ¥ 1010 (total) |
Energy Spread : single bunch | 0.4% (FWHM) |
:20 multi-bunch with ECS | ~ 0.3% (FWHM) |
Emittance gex : single bunch | 1.3 ¥ 10-4 (1s, at Inj.) |
: 20 multi-bunch | not measured |
Table. 2 Achievement of the Linac
In order to confirm the principle of this compensation scheme, the beam test was performed by using the 2856+4.32 MHz structure only at the beginning. Since the klystrons of the energy compensation system (ECS) were not ready at that time, the regular unit klystron was switched to the ECS structure. The frequency of the ECS is generated by the single side-band modulator which combines the signal of 4.32 MHz with the carrier of 2856 MHz. The measurement of beam energy for each bunch was done by using BPM after the bending magnet of the beam transport line. The multibunch signal from the BPM was measured by the digital oscilloscope of 1 GHz band width. After the adjustment of the beam timing with rf pulse, the phase of rf was set to an appropriate value to get a maximum deceleration for head bunches and a maximum acceleration for tail bunches. Then, the rf amplitude was set to get a flat energy distribution for all the bunches. The effect of the ECS is successfully demonstrated in the case of 10 bunches with 4 ¥ 109 each bunch and 20 bunches with 7 ¥ 109 each bunch intensity [1]. The calculated energy difference by the beam loading was 5% for 20 bunch case, the ECS by 2856+4.32 MHz frequency could compress it to 0.5% by 25 MW rf power.
After the installation of two sets of ECS modulator and klystron, a beam test of this regular ECS system was held on July 1996 using both 2856+4.32 MHz and 2856-4.32 MHz frequencies [10]. The OTR monitor combined with a bending magnet was installed for the measurement of energy and energy spread of multibunch beam in order to confirm the ECS performance. The bunch charge was limited to 1.5 ¥ 109 each by the radiation control alarm which was caused by an emitted radiation from the OTR monitor. The measured relative energy of each bunch by the BPM demonstrate the ECS compression performance shown in Fig. 3. The power level of the klystron was around 2 MW in this low charge compensation. The energy decrease at front of the bunches seems to come from the position shift caused from the side tail cut by the collimator.
The energy spread of each bunch, on the other hand, was measured by the OTR monitor with the 3ns gated camera [11]. Figure 4 shows the energy spread with ECS and without ECS in the case of 2.5 ¥ 109 each bunch. Although the measured spreads are scattered around 0.3% FWHM, there is no big difference even with this ECS. The observed waveform of multi-bunch beam by the wall-current monitor is shown in Fig. 5 in the case of the same charge. The monitor is placed at the downstream of the linac in front of the first bending magnet of the beam transport line.
After the commissioning of the Linac in 1995, the
installation of Damping Ring components was started in urgent.
Almost all the magnets, chambers and active stages were ordered
during 1995. The fabrication of these component are almost finished.
The installation will be finished till November 1996. Then, we
will have the beam commissioning of ATF Damping Ring on December
1996.
The author would like to acknowledge Professors Y. Kimura,
K. Takata and Y. Yamazaki, for their continuous encouragement
and support, and to Drs. S. Takeda and J. Urakawa for their
detailed discussion, support and good leadership. The author also
would like to thank to all the member of ATF group for their cooperation
on the linac construction and operation. The key persons of ATF
linac are; H. Matsumoto worked for the design and development
of all the high power rf components, M. Akemoto working on the
modulator development, T. Naito working on the multibunch thermionic
gun, profile monitors, magnets control and control hardware, K.
Oide working on the linac optics design and linac operation, K.
Kubo working on the linac operation, N. Terunuma working
on the control system, T. Korhonen working on the timing system
and the control system, F. Hinode working on the BPM software
and the control system, S. Kuroda working on the design of the
transport line optics, Y. Funahashi working on the support stages
of the transport line, S. Araki working on the alignment of transport
line magnets, Y. Takeuchi worked on the safety control system
of the linac, H. Hirayama and Y. Namito working on the radiation
control system, M. Yoshioka worked on the re-arrangement of the
assembly hall, positron experiment line and collaboration work.
The students came from universities;
A. Miura, M. Tawada, T. Asaka, M. Kagaya, S. Kashiwagi, T. Okugi,
K. Watanabe, C. Takahashi also participated in the construction
and operation of the linac. S. Morita and T. Matsui of E-Cube
co. are working on the high power rf system and the alignments.
T. Ishi of Kanto-Joho co. is working on the V-system software.
H. Ida of NKK corporation worked on the design of positron experiment
line. The success of ATF linac is a natural consequence of the
efforts of all the above people. The collaborations of CERN, DESY,
PAL, SEFT and SLAC as well as the domestic universities made a
great advance in the design and the operation of the linac.
[1] H. Hayano, "The KEK Accelerator Test Facility", Proc. of the 5th European Particle Accelerator Conference (Sitges), June 1996.
[2] H. Hayano, T. Asaka, H. Matsumoto, T. Naito, and S. Takeda, "An 80 MeV Injector for ATF Linac", Proc. of the 17th International Linac Conference (Tsukuba), Aug. 1994.
[3] T. Naito, M. Akemoto, T. Asaka, H. Hayano, H. Matsumoto, S. Takeda, J. Urakawa, and M. Yoshioka, "Multi-bunch Beam with Thermionic Gun for ATF", Proc. of the 17th International Linac Conference (Tsukuba), Aug. 1994.
[4] H. Matsumoto, M. Akemoto, T. Asaka, H. Hayano, T. Naito, and S. Takeda, "High Power Test of a High Gradient S-band Accelerator Unit for the Accelerator Test Facility", Proc. of the 17th International Linac Conference(Tsukuba), Aug. 1994
[5] H. Hayano, S. Takeda, H. Matsumoto, and T. Matsui, "Wire Alignment System for ATF Linac", Proc. of the 19th Linear Accelerator meeting in Japan, July 1994, p. 287.
[6] T. Korhonen, H. Hayano, H. Matsumoto, T. Mimashi, T. Naito, and J. Urakawa, "R&D of the ATF Timing System", Proc. of the 17th International Linac Conference (Tsukuba), Aug. 1994.
[7] M. Akemoto and S. Takeda, "Pulse Modulator for 85 MW klystron in ATF Linac", Proc. of the 17th International Linac Conference (Tsukuba), Aug. 1994.
[8] T. Naito, T. Asaka, H. Hayano, H. Matsumoto, and S. Takeda, "Bunch by Bunch Beam Monitor for ATF Injector Linac", Proc. of the 17th International Linac Conference (Tsukuba), Aug. 1994.
[9] F. Hinode et. al., "ATF Design and Study Report", KEK Internal 95-4, June 1995.
[10] S. Kashiwagi et. al., "Preliminary test of +/-df energy compensation system", in this conference.
[11] T. Naito et. al., "OTR monitor for ATF
linac", in this conference.