The Brookhaven 200 MeV linac serves as the injector
for the AGS Booster, as well as delivering beam to the Biomedical
Isotope Resource Center. During the past year, many linac systems
have been upgraded to allow operation at 2.5 times higher average
current (150 mA).
This was achieved by an increase in rep-rate from 5 to 7.5 Hz,
an increase in beam current from 25 mA to 37 mA, and a slight
increase in pulse width to ~530 ms.
Additional upgrades were made to improve reliability and modernize
old systems. This paper describes improvements made in the 35
keV and 750 keV beam transport, 200 MeV beam transport, rf transmission
line, rf power supplies, control systems, and instrumentation.
The AGS 200 MeV linac accelerates H-
ions for injection into the AGS Booster. The linac operates
at a 7.5 Hz rep-rate, and since the Booster takes only 4 pulses
every ~3 seconds, all remaining pulses are sent to the Biomedical
Medical Resource Center (BIRC). This facility produces radioisotopes
for the pharmaceutical and medical community, as well as supporting
a medical research program. In order to meet increased demand
for isotopes, we have nearly completed all phases of a program
to upgrade the average current out of the linac. The AGS has also
benefited from the improvements, since higher peak current out
of the linac improves Booster injection, and the reliability of
the linac was improved through modernization of systems. Most
of the improvements were funded as part of the BIRC project, through
DOE OHER, but parts have also been supported through AGS Department
Accelerator Improvement Projects. As a result of these improvements,
the average current out of the linac has increased by a factor
of 2.5, to 146 mA.
Table 1 shows the linac performance before and after the upgrade.
The improvements made to the various subsystems are described
in the following sections.
Table 1
Before Upgrade After Upgrade H- Beam Current 25 mA 37 mA Repetition Rate 5 Hz 7.5 Hz Beam Width 500 ms 530 ms Average Current 62 mA 146 mA
The beam from the magnetron surface-plasma H-
source is matched in to the RFQ by two pulsed magnetic solenoid
lenses. Until this year, the distance between source and RFQ was
2.1 m. This line also included an emittance measuring device and
a fast beam chopper. Because fast beam chopping is now done much
more effectively in the transport line after the RFQ, this 35
keV chopper box was removed to improve the matching into the RFQ.
In addition, calculations showed that matching could be further
improved if the first solenoid were moved closer to the source,
and the second solenoid closer to the RFQ. With the new distance
of 1.4 m, the first solenoid moved 4 cm upstream and the second
solenoid moved 4 cm downstream, the transmission through the RFQ
improved by ~10%, from the 70-80% range to 80-90%, depending on
source operating conditions. The emittance of the beam in front
of the RFQ was reduced by about ~20%. Typical current out of the
RFQ is now 65 mA, and the maximum current through the RFQ was
80 mA, 82% transmission. (In our case, the "transmission"
is the ratio of output current, measured 61 cm after the RFQ,
to input current measured 55 cm before the RFQ).
There is a 6 m transport line from the RFQ to linac, to accommodate a pulsed dipole where polarized H- comes from a second beamline, and a fast beam chopper. There are three bunchers and 13 quadrupoles in this line. Transmission in this line was only ~75%, with losses early in the line caused by the fact that the first quadrupole after the RFQ was not close enough to catch the beam before it got too large. In order to reduce the beam divergence quickly coming out of the RFQ, a 1.1 cm aperture, 3.5 cm long permanent magnet quadrupole was placed in the endflange of the RFQ, only 2.1 cm from the RFQ vane tip. In addition, this quadrupole can be moved transversely while running beam, via micrometer adjustment outside vacuum, in order to steer the beam. A picture of the RFQ endflange with PMQ is shown in figure 1.
Additional changes in the line were to move the first
quadrupole triplet 9 cm closer to the RFQ, and to convert a final
quadruplet (which had been running as a triplet), into a real
triplet. We also removed all magnets from the line and had the fields precisely measured by the RHIC magnet group. All magnets were carefully surveyed when reinstalled, particularly trying to eliminate quadrupole rotations, which leads to emittance growth of the beam. With these improvements, the transmission from the RFQ to linac was improved to ~85%. We believe that the remaining loss comes from the 12 "grids" (made of thin tungsten strips) in the line, in the three buncher cavities.
With this 50% higher current at the linac entrance,
the linac transmission remained the same, with ~70% being captured
in the first tank. This agrees with calculations of the line,
and comes from the fact that the line is too long to match longitudinally
with only three bunchers. The calculations show that with a fourth
buncher the capture into the linac could be >95%.
There were both vacuum-related and beam optics improvements in the transport line between the end of the linac and the BIRC target. Most of the vacuum components in the line were replaced. O-rings were eliminated, and the line now uses all conflat flanges. Aluminum pipe was used in much of the line to minimize activation. Pumping of the line was increased, with new turbo pumps and ion pumps. Apertures in the line were increased wherever possible, and most of the line has either 6" or 8" diameter beampipe.
Details of the optics of the line are given in another
paper at this Conference.[1] Briefly, there are two bends between
the linac and BIRC target, and a quadrupole was added to make
these bends achromatic. Further downstream, two octupoles and
two quadrupoles were added in order to produce a uniform current
density on the BIRC targets, to prevent melting of some target
materials at this increased beam power. While we have been able
to produce flattened beam profiles on an upstream profile monitor,
progress on producing a flat distribution on target has been slow,
due to the long turnaround time (1 day) on profile measurements
at the target location (via activation of foils and counting).
In order to improve reliability at the increased linac duty factor, all the 12" coaxial transmission line was replaced. Up to 6 MW peak power is fed from each of the nine rf systems, through a 3 db power split, and into two ports on each of the nine accelerating cavities, a total of over 200 m of transmission line for the full linac. Our 25 year old system had disadvantages of having aluminum inner conductor, spring ring rf contacts, and was unpressurized. The new transmission line system was built and installed by Dielectric Corporation. It has a copper inner conductor and an aluminum alloy outer conductor, is pressurized to 15 psi with dry air, and the connectors for the center conductor are EIA-type finger contacts. We replaced the full system, including the 3 db power splitters, waster loads, breakaway and telescoping sections, and reflectometers. A hybrid phase shifter (mechanically variable) was replaced with a transmission line section of optimum length in each system.
The removal of the old transmission line took one week, and the actual installation time for the new system was approximately three weeks, although total time to fully complete, test and debug was three months. The new system has operated very reliability, with low insertion loss, very low probability of voltage breakdown, and improved S-parameters.
7835 Anode Power Supply
The 6 MW power amplifiers for the linac use Burle 7835 triodes. At the increased current and duty factor of the linac, some of the 60 kV, 2 A, 7835 anode power supplies would be running at their 2 A limit, a concern for reliability. In addition, these power supplies, constructed in 1968, are oil filled units that are outside the linac building, connected to capacitor banks by a long high voltage transmission system. Servicing the power supplies can be a problem because of weather and the need for a crane. Also, the placement of the power supplies would not meet current code requirements for fire protection or oil containment. It was felt that with the present technology, a dry type power supply could be built, and in order to meet any future requirements, we settled on a 50 kV, 5 A supply.
While several vendors offered high frequency switching supplies, the final selection was a conventional 6 pulse primary phase controlled dry type transformer rectifier (TR) set, built by Universal Voltronics (UVC). To save money, the power supplies were housed in existing linac cabinets that formerly housed the charge control amplifiers. These cabinets are 4x8x8 feet and are fully compatible with the existing lifting fixtures, building crane, and floor space requirements.
The high voltage secondary coil of the transformer presented the greatest technical challenge. In the final design, each of 6 secondary coil assemblies was divided into two individual coils, lowering the layer to layer voltage by a factor of two. The coils were then wound with vertical spacers to allow the epoxy to flow between each of the layers. The final, completed 250 watt transformer assembly is compact, measuring 1.5'x4'x4'. None of the temperatures on the transformer secondary exceeded 60 C after 24 hours running.
The power section is a straightforward six pulse primary phase control. The voltage and current regulating loops are compensated for the capacitive load. The power supply charges the capacitor bank at a constant current (current mode) until the preset voltage is reached (voltage mode).
Seven power supplies have been delivered to BNL and
tested, with the remainder due shortly. They will go online in
January '97.
4616 Anode Power Supply
The Burle 4616 tetrode is used in the driver stage
of the linac rf system. The anode power supply is being upgraded
to improve the feedback control, employing both current and voltage
feedback, and replace unavailable SCR controllers.
PLC Controls for RF Systems
The linac is made up of 9 identical rf stations. Each station has several subsystems, including the driver, 7835 filament supply and cavity, 50 kV supply, capacitor bank, modulator, and local control station (LCS). Each of the subsystems has individual control buckets for AC and high voltage logic. These buckets were designed and built in 1968 around 7400 TTL series components. Replacing these control buckets with more modern components is a necessity because many of the components are no longer available.
We are beginning to implement a new control system, utilizing programmable logical controllers (PLC's). It is designed for fully independent operation of each rf system, flexibility and reliability. An Allen Bradley 5/40 processor was chosen for each LCS. A 5/50 ethernet processor was selected for the control room. Each of the 5/40's can scan the subsystems of a system (scanner mode), or be scanned by the host in the control room (adaptor mode).
There are 3 networks that make the backbone of the
system. The first network is responsible for the data collection
and control of each station. The 5/40 in the LCS scans the subsystems
of a station. To minimize the wiring, each of the subsystems has
a miniature processor (Allen Bradley flex I/O) that multiplexes
the data at 230 kbaud for the 5/40. A single twisted pair links
all of the subsystems of a mod together. The subsystems are connected
together via the Allen Bradley Remote I/O network. The second
and third networks are links between each of the systems. The
DH+ network runs at 57 kbaud and is responsible for the remote
monitoring and control of all 9 systems. The Allen Bradley graphical
interface program, Control View, is used to control the supplies.
An additional remote I/O network allows the 5/40 E in the control
room to monitor each mod at 230 kbaud for fast global control.
For example the 5/40 E can turn off all the 50 kV supplies at
the same time if needed.
This past year the original 25-year-old Linac control system was replaced with a modern modular system fully integrated into the existing AGS distributed control system. Unix workstations provide the operator interface, and are networked using ethernet to front-end computers which are implemented using VMEbus components. A front-end computer located in the Linac Control Room sources four high speed serial communication links using the Datacon field bus, a long-standing BNL standard. Although an old system, Datacon is extremely robust and noise immune, can operate over 2000 ft. of coaxial cable, and is relatively inexpensive. Each Datacon link can address up to 256 devices, delivering a 24-bit command and accepting a 32-bit reply. All devices are accessed for each Linac pulse (7.5 Hz), and in particular, device setpoints are rewritten for each pulse; thus any sequence of different Linac clients (Booster, BIRC) requiring possibly different settings can be accommodated - a feature termed pulse-to-pulse modulation (PPM). The individual devices are interfaced to the Datacon link via dual-channel cards housed in crates at 11 locations along the Linac. We are controlling and/or monitoring over 400 devices.
At the heart of the Datacon field bus system is the
VME Datacon engine. This device was developed at BNL using modern
field programmable gate array (FPGA) and RISC processor technology.
The Datacon engine supports multiple Datacon channels with each
Datacon channel capable of addressing the full Datacon address
space. The Datacon engine has an on board timeline decoder and
local memory so that all Datacon transactions can be preloaded
into tables, sent on previously programmed timing events, and
data returned and stored without intervention by the VME processor.
This has resulted in a many fold increase in data throughput compared
to older Datacon implementations.
There are two aspects of the linac timing system which will be upgraded in FY'97. The "local" timing system provides specialized "fixed" delays, generates sequences of triggers required for rf systems, etc., and checks to make sure that external triggers coming in to the linac are in the proper sequence. It will allow us to time shift the triggering of rf power to individual accelerating cavities, and with downstream cavities time shifted out of beam time we can run at different energies on a pulse-to-pulse basis. This local Linac timing hardware will consist of Altera PLD chips for designing the logic controls. An 8051 microcontroller chip will provide the processing of data to and from the PLD chips. A RAM chip will store the data for each user. The microcontroller will control the data flow. A PC with control software will provide the interface.
A second part of the timing system provides external
trigger signals (from downstream accelerators) to the linac local
timing, as well as triggers to some specific linac hardware. This
new Linac timing system will be an encoded timeline using RHIC
generation VME timing system modules. With these modules a Linac
timeline can be built without hard wiring or hard coding. The
timeline can be changed by command from computers on the accelerator
control network and/or by cable changes between modules at the
generator. The timeline generator will be located in the Linac
control room and the encoded timeline will be distributed along
the linac via fiber optic cables. Decoder/delay modules, fully
programmable through the VME processor, connect directly to the
timeline and provide decoded pulses from events, or can provide
delayed outputs from an event.
A stripline position monitor was added between the
bends to the BIRC target, at a high dispersion point, to allow
monitoring of the linac energy. As suggested by P. Ostromouv (INR),
a diagnostic was added at the end of linac cavities #1 and #4,
to aid in the setup of the phase and amplitudes. This is a series
of Al plates of appropriate thickness, each electrically isolated
and on which the current can be read. Successive plates will stop
partially accelerated particles from successive cavities, allowing
one to do phase and amplitude scans for coarse setup of the tanks.
Finally, a third wire at 45o was added to two SEM units,
giving beam profiles in 3 projections by stepping through the
beam. With this, we are able to get 3-dimensional tomographic
reconstructions of the beam distribution, as described in [2].
With improvements in beam transport through the 35
keV and 750 keV lines, we can now operate at currents 50% higher
than previously. The average current out of the linac has reached
our goal of 146 mA,
and still higher currents should be possible. Most of this past
running period was at reduced beam pulse width, due to BIRC target
limitations. (They expect to be able to run at full average current
next year). Therefore, we can not yet say if reliability will
suffer over long periods at 150 mA,
but so far indications are that there is an overall improvement
in linac reliability.
We acknowledge the excellent work on this project
of the entire Linac staff, the AGS controls group, and the AGS
vacuum group. We also thank the RHIC magnet group for their assistance.
[1] A. Kponou, et al., "A new optical design for the BNL isotope production transport line", these proceedings.
[2] D. Raparia, et al., "Comparisons between
modeling and measured
performance of the BNL linac", these proceedings.
*Work performed under the auspices of the U.S. Dept.
of Energy.